Hi,
You are fully complied with procedure already as you mentioned below, but I think you should check the welding condition like wind prevent,..or preheat before welding…
Wish you success
Best Regards,
Vu Duc Thuan
Phone: +84(0) 983 017 936
From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of jiji lal
Sent: Saturday, April 13, 2013 12:07 PM
To: materials-welding@googlegroups.com
Subject: [MW:17372] PRE HEAT PROCEDURE OF E 7016 -1 ELECTRODE
SIR,
I'm engaged with welding of API 5LX 80 grade pipeline for regassified LNG transmission . We do Tie-in method using SMAW+FCAW.
For root pass welding we use E7016-1 electrode after pre heating 250 degree for 2 hr in mother oven and maintain 100 degree in holding oven . during RT interpretation severe hollow bead and porosity observed in root .hence PMC sent almost all joints for repair.now it becomes a serious issue and I think ,the pre heat method was not proper. kindly advice me in this issue.
Mr.Jijilal k .m
qa/qc dept. tecpro ltd.
kochi.
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
No comments:
Post a Comment