Project Quality Control is part of quality management which focuses on fulfilling requirement of quality (3.2.10).
Quality Inspection Plan, you may call it as Inspection and Testing Plan, is element of project quality plan focuses on minimum inspection and testing to verify the conformance of product and or service to the specified requirements in the contract and reference specification.
Inspection and testing plan specifies project activity description, quality control activity, reference document, acceptance criteria and inspection level definition and coordination.

let this helps you

rgds

2011/4/17 aslam khan <aslamkhan4u@gmail.com>
hi friends,
dear friends ,what is difference between QIP(quality inspection plan)
and PQP(project quality plan )? thanks in advance .

best regards
ASLAM

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...