Re: [MW:10656] hydro testing of Pipelines

Halo Sohaib

Please see attached to get the answer

Rgds

2011/4/12 SOHAIB GHNAIMAT <sohaib_cegco@yahoo.com>



Team,
 
We have just completed the hydro test for 66" underground Pipeline the temperature at the begining of the test / Holding time was 13 Deg C. and after 14 hrs of the holding period ( 24 hrs ) the temperature was 24 deg C.
 
what will be the change in pressure ?
 
Regards,

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...